NW China province to transmit power to Tibet
  • Soccer Chief Took Millions: Says Report
  • Real-name Cell Phone Reg. Faces Weak Implement
  • 'Detective Dee' Premieres in Venice
  • Star melts at wax treatment
  • Embrace Fantastic Xinjiang during its Best Season
  • Chinese Gov't Reviews Retirement Age
  • http://english.dbw.cn銆€銆€ 2010-09-16 13:46:54
     

    Next, a 400 KV transmission line from Golmud to Lhasa, capital of Tibet Autonomous Region, will be hung;

    Third, a 220 KV grid facilities within Tibet will be built.

    The transmission line will run 1038 km from Golmud to Lhasa. About 900 km of the line will be built on lands that are at least 4,000 meters above sea level, making it the longest power transmission line ever constructed at such high altitudes.

    Experts warn, however, that harsh conditions on the plateau might affect the workers' health along with their efficiency.

    Currently, more than 4,500 workers are at the sites, involved in preparatory works. The number of workers is expected to reach 20,000 during its peak time, according to statistics from the construction headquarters.

    The project has allocated 300 million yuan for medical care and environmental protection. First aid stations are being built every 25 to 30 km and clinics are to be set up every 100 km along the line. Workers will be trained in bases in Golmud and Lhasa to become accustomed to the environment before going to the work sites, said Fa Tao, head of the project's medical and life support department.

    "Our goal is to ensure three zeroes - zero death, zero disability and zero permanent health damage for workers of the project," he said.

    Another challenge for those involved in the project is to avoid affecting Qinghai-Tibet plateau's fragile ecology. "Whenever there is a conflict between construction and ecology, we will make way for environmental protection," said Yu Xinqiang, head of the construction headquarters.

    The soil, along with the plants in it, will be taken away and preserved before a transmission tower is constructed. Then the soil and plants will be returned to its original site, according to the construction plan.

    Workers are strictly prohibited from hunting or disturbing animals on the plateau. Also, transmission towers should be located away from animal habitats, according to the plan.

    A section of 550 km of the transmission line will be built on frozen soil that could become unstable due to temperature changes. "Construction on frozen soil is difficult, but we have developed some technologies to ensure the project progresses as planned," said Ding Yansheng, head of the construction headquarters' technology department.

    Experts note that with the experience of constructing the Qinghai-Tibet railway line, the world's highest and longest railway on a plateau, most of the project's challenges have previously learned solutions.

    Author锛? 銆€銆€銆€Source锛? xinhua 銆€銆€銆€ Editor锛? Yang Fan