The Three Gorges five-stage ship lock has been in safe operation since the dam began its 175-meter trial water retaining. So far no navigation accidents have been reported in the water area.
With the rising of water levels in the Three Gorges region, the four-stage ship lock operation was upgraded to the five-stage on September 25th. It takes 30 minutes more than the previous four-stage ship lock operation for ships to go through the gates.
The Three Gorges five-staged ship lock is the largest of its kind in the world, which can raise and lower ships to cross the huge dam. Essentially it is a giant ship elevator capable of lifting a ship of 14,000 tons to a maximum height of 113 meters.
Four-stage ship lock operation is required when the Three Gorges water levels stand between 135 and 152.4 meters. When the water level rises above 152.4 meters and below 156 meters, the ship lock of the dam will be in the critical period of upgrading from 4 to five stage.
Between September 15th and October 20th, some 5,600 ships had crossed the Three Gorges ship lock with 6.76 million tons of cargo and 836,000 passengers, equivalent to the volume of the previous month, when the dam had not started restoring water.
|